News and Announcements

Posted on: September 22, 2020

9-22-20 Cleveland Massillon Road Update

Golf cart tunnel sections are being placed.  

Read on...

Cleveland Massillon Road News and Announcements
Posted on: September 21, 2020

9-21-20 Cleveland Massillon Road Update

Finishing grades for the 140 foot box culvert at Schocalog Creek.  

Read on...

Cleveland Massillon Road News and Announcements
Posted on: September 18, 2020

9-18-20 Cleveland Massillon Road Update

Finished work on the golf cart tunnel foundation. 

Finished work on box culvert foundation for Schocalog Creek.  

Read on...

Cleveland Massillon Road News and Announcements
Posted on: September 16, 2020

Cleveland Massillon Road 9-16-20 Update

Foundation for golf course tunnel expansion being placed.

Starting work for the box culvert for Schocalog Creek.  

Read on...

Cleveland Massillon Road News and Announcements
Posted on: September 11, 2020

Tree Trimming and Removal Starting 9-11-20

TriMor Construction has begun tree trimming and removal for the Cleveland Massillon Road Project. Delays are expected and it is suggested that motorist use an alternate route.

Cleveland Massillon Road News and Announcements
Posted on: September 11, 2020

9-11-20 Work Continues

Road will close on Monday 9/14/20 at 7:00 A.M. for 45 days.  Please follow posted detours.  

Northbound Detour Map

Southbound Detour Map

Read on...

Cleveland Massillon Road News and Announcements
Posted on: September 10, 2020

9/10/20 - Construction Starts on Cleveland-Massillon Road

Wing walls were removed and ground excavation to extend the tunnel another 40 feet with new wing walls has begun.  Tree removal has also started for the new box culvert at Schocalog Creek.

Please remember that this is a construction zone and delay...

Read on...

Cleveland Massillon Road News and Announcements
Posted on: September 10, 2020

9/10/20 - Expect Delays On Cleveland-Massillon Road

Due to Frontier moving their fiber lines, delays are expected on Cleveland-Massillon Road. Please watch for flaggers.

Cleveland Massillon Road News and Announcements
Posted on: August 7, 2020

Cleveland Massillon Road Construction and Closure

The road will close on September 14, 2020 for 45 days from Elgin Drive/Rosemont Blvd. north to Bywood Drive for the removal of a pipe for Schocalog Creek and the installation of a box culvert.  Local businesses can be accessed from Route 18 and C...

Read on...

Cleveland Massillon Road News and Announcements
Posted on: June 25, 2020

Cleveland-Massillon Pre-Construction Meeting Held

TriMor Corp. submitted a schedule of work with a tentative start date of September 1, 2020.  The COVID-19 virus has delayed materials to properly start the project.  All submittals are being reviewed by The City of Fairlawn and EDG (our ...

Read on...

Cleveland Massillon Road News and Announcements
Posted on: May 18, 2020

Construction Bids

Ohio Edison is almost complete with utility relocation.  Spectrum and Frontier will be moving their infrastructure over the next month.  

Cleveland Massillon Road News and Announcements
Posted on: March 17, 2020

Update to Cleveland Massillon Utility Work

Dominion East Ohio will be finished this week. Ohio Edison is at the intersection of Elgin Drive and Cleveland Massillon Road for two weeks. Summit County D.S.S.S. project is restored from Cleveland Massillon road to the east.

Cleveland Massillon Road News and Announcements
Posted on: March 11, 2020

Utility Relocation Continues

Ohio Edison pole relocation has begun. Also, the Federal Highway Commission has approved the project and bidding will begin soon.

Cleveland Massillon Road News and Announcements
Posted on: March 2, 2020

Sewer Line Work

Sewer line work at Rothrock Road will be crossing Cleveland-Massillon Road Monday March 2nd and Tuesday March 3rd between 10:00 PM and 6:00 AM. Expect delays.

Cleveland Massillon Road News and Announcements
Posted on: February 24, 2020

Work Scheduled for Week of February 24, 2020

Ohio Edison will begin their work in the right of way the week of March 2, 2020.  

On another note, Sanitary sewer construction will impact the intersection of Cleveland-Massillon Road and Rothrock Road in the weeks to come.  This is a se...

Read on...

Cleveland Massillon Road News and Announcements
Posted on: February 4, 2020

Plans, Specifications and Estimates

On January 31, 2020, The Local Let Plans, Specifications and Estimates package was sent to ODOT for final review. Dominion is placing materials and will start construction this week.

Cleveland Massillon Road News and Announcements
Posted on: January 27, 2020

Work Scheduled for Week of February 3rd

The Rothrock Sanitary Sewer Project from Grace Church to approximately 500’ west of the Rothrock/Cleveland-Massillon Road intersection will begin the week of February 3, 2020.

Dominion Gas will also start moving their gas lines the week of Februa...

Read on...

Cleveland Massillon Road News and Announcements
Posted on: December 23, 2019

December 23, 2019

Ohio Edison and Dominion Gas are scheduled to move their infrastructure in January and February 2020.

Cleveland Massillon Road News and Announcements
Posted on: November 18, 2019

November 18, 2019

Other utilities are in the process of moving their lines.

Cleveland Massillon Road News and Announcements
Posted on: October 3, 2019

Utility Relocation Work To Be Done on Cleveland-Massillon Rd.

Employees from First Energy, FairlawnGig, Dominion East Ohio, and other utilities will be working in the expanded right of way.

Any questions or concerns may be directed to the Fairlawn Department of Public Service at 330-668-9550.

Read on...

Cleveland Massillon Road News and Announcements
Posted on: August 26, 2019

August 26, 2019 Update

We currently have nine parcels that have been successfully closed for the project.

Cleveland Massillon Road News and Announcements
Posted on: May 21, 2019

May 20, 2019

Three more pieces of right of way acquisition have been successfully negotiated and have passed legislation.  This brings our total to 7 parcels.

Cleveland Massillon Road News and Announcements
Posted on: May 13, 2019

May 13, 2019

We have successfully negotiated two additional pieces of right of way acquisition and have passed appropriate legislation for these purchases. 

Cleveland Massillon Road News and Announcements
Posted on: April 22, 2019

April 22, 2019

We have successfully negotiated our first piece of right of way acquisition and have passed appropriate legislation for the purchase.

Cleveland Massillon Road News and Announcements
Posted on: April 10, 2019

April 8, 2019

Appraisals are still in the process of being submitted for right of way acquisition.

Cleveland Massillon Road News and Announcements
Posted on: March 25, 2019

March 25, 2019

All land owners have been contacted for right of way acquisition. Appraisals are in the process of being submitted.

Cleveland Massillon Road News and Announcements
Posted on: February 22, 2019

February 22, 2019

Right of Way Acquisition phase of the Cleveland Massillon Road Widening Project has begun.

Cleveland Massillon Road News and Announcements