4-5-21 Cleveland Massillon Road Update
Grading of the right of way is underway. Please watch out for work crews and obey all flaggers and signage. Read on... -
4-13-21 Cleveland Massillon Road Update
East side roundabout construction. The shape of the design and base have been placed. Please watch out for work crews and obey all flaggers and signage. Read on... -
4-7-21 Cleveland Massillon Road Update
Stabilization of the roadway is taking place. Please watch out for work crews and obey all flaggers and signage. Read on... -
3-30-21 Cleveland Massillon Road Update
New water vault being installed at Crosspoint Church. Please watch out for crews and obey flaggers in the work zone. Read on... -
3-26-21 Cleveland-Massillon Road Update
Curb is being installed between Rothrock Road and Rosemont Boulevard. Please watch out for crews and obey flaggers and signage. Read on... -
3-19-21 Cleveland Massillon Road Update
Work is starting on the Rothrock Road leg of the roundabout. Please watch out for crews and obey flaggers and signage. Read on... -
3-11-21 Cleveland Massillon Road Update
Work continues on Cleveland Massillon Road. Please watch out for crews and obey flaggers and signage Read on... -
2-26-21 Cleveland Massillon Road Update
Base removal continues on the westside of Cleveland Massillon Rd. Please watch out for workers and flaggers! Expect delays through the construction area. Read on... -
2/4/21 Cleveland Massillon Road Update
Work continues on Cleveland Massillon Road. Please watch out for crews and obey flaggers and signage Read on... -
2/2/21 Cleveland Massillon Road Update
Work continues on Cleveland Massillon Road. Please watch out for crews and obey flaggers and signage. Read on... -
1/19/21 Cleveland-Massillon Road Update
-
1/13/21 Lane Striping on Cleveland Massillon Road
Traffic will be down to one lane today due to lane striping. Please watch out for work crews and obey all flaggers. Avoid the area if at all possible. -
1-7-21 Cleveland Massillon Road Update
Construction has resumed on Cleveland Massillon Road now that the holidays are over. Read on... -
12-18-20 Cleveland Massillon Road Update
Crews are cleaning up the project for the holiday break. Read on... -
12-4-20 Cleveland Massillon Road Update
Manhole has been set at the proposed roundabout. Grading for the west side of the roundabout will begin next week. Read on... -
11-24-20 Cleveland Massillon Road Update
Storm sewer nearing Rothrock Road. Read on... -
11-13-20 Cleveland Massillon Road is OPEN
As of 8:00 PM Friday November 13th, Cleveland Massillon Road has been reopened to traffic. North and southbound lanes are narrowed - PLEASE USE CAUTION -
11-12-20 Cleveland Massillon Road Emergency Closure
Cleveland Massillon Road is closed due to an emergency gas line rupture. Please avoid travel through this area. -
11-5-20 Cleveland Massillon Road Update
New speed limit signs have been posted through the construction area. Please slow down and use caution as the lanes are narrow. Flaggers are on site. EXPECT DELAYS Read on... -
11-4-20 Cleveland Massillon Road Update
Construction south of Elgin Drive. Please use care through the construction zone. EXPECT DELAYS Read on... -
11-3-20 Cleveland Massillon Road Update
Work will be done on Rosemont Boulevard. Flaggers will be in the construction area. EXPECT DELAYS. -
11-2-20 Cleveland Massillon Road Update
Cleveland Massillon Road is officially open to through traffic. We ask that you drive with caution as construction crews are continuing work on the remaining project. Read on... -
10-30-20 Cleveland Massillon Road IS OPEN!
-
Urgent Update on Cleveland-Massillon Road Traffic
-
10-30-20 Cleveland Massillon Road Update
-
10-23-20 Cleveland Massillon Road Update
Work continues on Cleveland-Massillon Road. Please follow all signage and posted detours. Read on... -
10-22-20 Cleveland Massillon Road Update
Cleveland Massillon Road is still under construction and closed. Please obey all signage and follow all posted detours. Read on... -
10-21-20 Cleveland Massillon Road Update
-
10-17-20 Cleveland Massillon Road Update
The roadway along the curve is starting to take shape. Read on... -
10-14-20 Cleveland Massillon Road Update
-
10-8-20 Cleveland Massillon Road Update
Work is progressing along Cleveland-Massillon Road. The road is still closed. Please obey all signage and follow posted detours. Read on... -
10-6-20 Cleveland Massillon Road Update
Please remember that Cleveland Massillon Road is closed. Obey all signage and posted detours. Read on... -
10-5-20 Cleveland Massillon Road Update
Please remember that the road is closed and to follow all signage and posted detours. Read on... -
10-2-20 Cleveland Massillon Road Update
Please obey all signage and follow posted detours. Read on... -
9-29-20 Cleveland Massillon Road Update
Cleveland Massillon Road is still closed. Please obey all signage and follow posted detours. Read on... -
9-28-20 Cleveland Massillon Road Update
Work is continuing on schedule for the Cleveland Massillon Road project. Please obey all signage and follow posted detours. -
9-25-20 Cleveland Massillon Road Construction Update
Please remember that Cleveland Massillon Road is closed. Obey all traffic control devices and follow posted detours. Read on... -
9-24-20 Cleveland Massillon Road Construction Update
Please remember that Cleveland-Massillon Road is closed. Obey all traffic control devices and follow posted detours. Read on... -
9-23-20 Cleveland-Massillon Road Update
Cleveland Massillon Road is closed. Please obey all signage and follow the posted detours. Read on... -
9-22-20 Cleveland Massillon Road Update
Please remember that Cleveland Massillon Road is closed. Obey all signage and posted detours. Read on... -
9-21-20 Cleveland Massillon Road Update
Please remember that Cleveland Massillon Road is closed. Obey signage and follow the posted detours. Read on... -
9-18-20 Cleveland Massillon Road Update
Below are pictures and descriptions of the work being performed. Please remember that the road is closed and to follow posted detours. Read on... -
Cleveland Massillon Road 9-16-20 Update
See below for pictures and descriptions of work being performed. Please remember that the road is closed and to follow posted detours. Read on... -
Cleveland-Massillon Road Closed September 14, 2020
Cleveland-Massillon Road is officially closed for 45 days as of Monday, September 14, 2020. Please follow posted detours. Read on... -
Tree Trimming and Removal Starting 9-11-20
TriMor Construction has begun tree trimming and removal for the Cleveland Massillon Road Project. Delays are expected and it is suggested that motorist use an alternate route. -
9-11-20 Work Continues
Frontier will continue with their fiber move this weekend (9/12 - 9/13). Expect delays. Read on... -
9/10/20 - Construction Starts on Cleveland-Massillon Road
Construction began on September 9th on the extension of the golf cart tunnel. Read on... -
9/10/20 - Expect Delays On Cleveland-Massillon Road
Due to Frontier moving their fiber lines, delays are expected on Cleveland-Massillon Road. Please watch for flaggers. -
Cleveland Massillon Road Construction and Closure
Cleveland Massillon Road construction will begin on September 8, 2020 with mobilization and maintenance of traffic set up. Read on... -
Cleveland-Massillon Pre-Construction Meeting Held
A Pre-Construction meeting was held on Tuesday June 23 with the selected contractor, TriMor Corp. Representatives from Ohio Dept. of Transportation (ODOT), Summit County, Copley Twp., the inspection firm, and utilities for the project were in attendance. Read on... -
Construction Bids
Bids were received on Friday May 8, 2020. After review, TriMor Corporation was the lowest and most responsive bid at $8,133,955.56. The bid approval from City Council will be presented at the May 18, 2020 Council Meeting. Read on... -
Update to Cleveland Massillon Utility Work
Dominion East Ohio will be finished this week. Ohio Edison is at the intersection of Elgin Drive and Cleveland Massillon Road for two weeks. Summit County D.S.S.S. project is restored from Cleveland Massillon road to the east. -
Utility Relocation Continues
Ohio Edison pole relocation has begun. Also, the Federal Highway Commission has approved the project and bidding will begin soon. -
Sewer Line Work
Sewer line work at Rothrock Road will be crossing Cleveland-Massillon Road Monday March 2nd and Tuesday March 3rd between 10:00 PM and 6:00 AM. Expect delays. -
Work Scheduled for Week of February 24, 2020
Dominion East Ohio Gas should be finishing up work in the right of way this week. Due to the work being done by Dominion, trees along the golf course property were cut down to facilitate the new gas lines. Read on... -
Plans, Specifications and Estimates
On January 31, 2020, The Local Let Plans, Specifications and Estimates package was sent to ODOT for final review. Dominion is placing materials and will start construction this week. -
Work Scheduled for Week of February 3rd
-
December 23, 2019
We are down to the final 2 acquisition cases. Read on... -
November 18, 2019
Utility move along Cleveland-Massillon Road is proceeding. FairlawnGig has been moved. Read on... -
May 20, 2019
-
May 13, 2019
-
April 22, 2019
-
April 8, 2019
-
March 25, 2019
All land owners have been contacted for right of way acquisition. Appraisals are in the process of being submitted. -
February 22, 2019
Right of Way Acquisition phase of the Cleveland Massillon Road Widening Project has begun.